21 Mar 2018

A rapidly-deployable temporary fence line has helped a construction giant deliver a key installation for National Grid to help meet London’s increasing energy needs. A new 400kV Gas Insulated Switchgear electricity substation has been constructed as part of the EAN Framework and connected to a £1bn 32km electricity superhighway deep below the capital.

Perimeter security mesh manufacturer Zaun Ltd provided 155 metres of high-security Rapid Deployable System (RDS) fencing for temporary protection of the construction works. Zaun subsidiary Binns Fencing installed the system.